Project Overview

Cheshire and Wirral Partnership NHS Trust provides mental health, substance misuse, learning disability and community physical health services.

We were appointed as CDM Coordinator following the successful delivery and support of Dane Ward & Mary Dendy projects at Macclesfield General Hospital. This project consisted of internal remodelling of the existing eating disorder unit at Springview, Clatterbridge Hospital.

The works were undertaken within a fully operational and sensitive live environment.

The project lasted 8 months on site due to the sensitive nature of the programme and associated enabling works. The project budget was £750,000.00 and was delivered on time and within budget.